NOTICE: Waldemar Pumphouse Valve Replacements - October 2021

The Township of Amaranth recently awarded H2Ontario Incorporated the contract to replace valves in the Waldemar Pumphouse. The project is scheduled to take place over the next few weeks from Tuesday, October 12, 2021 to Friday, November 5, 2021. The project is restricted to the area around the Waldemar pumphouse with all work areas fenced off from the public. Work will take place between 7:30AM to 4:30PM, Monday to Friday. Traffic and pedestrian control measures will be put in place on the laneway to Waldemar Park but there will be no interference with Station Street. Project Contacts are listed below in case of issues/complaints.
 
Project Contacts:
 
Paul Korczynski, Site Supervisor, H2Ontario Inc., 519-503-2974 (cell)
Marty Zorgel, Construction Inspector, R.J. Burnside & Associates Limited, 519-217-2718 (cell)

Contact Us